Chapter 9 - Flexible Budgets and Performance Analysis - Questions - Page 410: 9-2

Answer

Flexible budget is a report showing estimates of what revenues and costs should have been, given the actual level of activity for the period. A static planning budget is prepared for only a single level of activity and is not subsequently adjusted.

Work Step by Step

Flexible budget is a report showing estimates of what revenues and costs should have been, given the actual level of activity for the period. A static planning budget is prepared for only a single level of activity and is not subsequently adjusted.